October 5, 2022

As part of the long-term plans for the area, the site has planning permission to be redeveloped for housing to provide 251 homes. This is part of the existing outline planning permission for the regeneration of the Brent Cross Cricklewood area. Not only will this mean new housing sooner in the overall development programme, but also has the potential to have a positive impact on air quality and traffic in the area by removing the HGV traffic from Claremont Road and other surrounding residential neighbourhoods.

Construction updates: 

  • Chase New Homes development consists of three blocks. Block 1 will consist of six storeys, whilst Block 2 will have five, and Block 3 will have eight.
  • Construction of Block 1 has reached the second-floor concrete slab stage, with scaffolding scheduled to start in August and bricklaying works to begin in September.
  • Block 2 has reached the ground-floor concrete slab and bricklaying works will begin in December.
  • Works on Block 3 (which is located adjacent to the railway line) are scheduled to begin in August.
  • Groundworks across the site are nearing completion, with all new roadways now in place.

The Chase New Homes team is working hard to keep noise, dust, and vibration levels to a minimum and are monitoring them continuously.

Contacts Us

If you have any questions or concerns about the works, please contact the project manager Alex Henton at enquiries@chasenewhomes.co.uk or via telephone 01707 660660