Tilling Road
View work schedule
From Monday 7 July 2025, works will start at the junction of Tilling Road and Claremont Road so that we can deliver improvements to the highway in the area.
The works are an essential part of the wider Brent Cross Cricklewood regeneration programme, increasing capacity on our roads, and making it much easier and safer for pedestrians to get around the area.
More details about the works and schedule can be found below.
Works commencing: Monday 7 July 2025
Contractors: FM Conway
Work programme:
- The works have been split in two phases to keep traffic flowing and to minimise disruption as much as possible.
- The first phase of works includes junction widening, improvements to the footways and improvements to street lighting. These works will require part lane closures on Tilling Road and Claremont Road.
- The second phase of works consists of road resurfacing and replacing road markings, which will be undertaken overnight for two weeks at the end of November 2025 and require a road closure.
Before and throughout the duration of the works, clear signage and safe pedestrian crossing facilities will be provided, as well as temporary traffic signals to keep traffic flowing.
Bus stops:
Some bus stops on Claremont Road and Tilling Road will be temporarily relocated close to their existing stop to ensure that bus services can still operate as usual.
Contact:
If you have any questions or concerns regarding these works, you can contact us via email at TransformingBX@Barnet.gov.uk