Geron Way
As part of the Brent Cross Cricklewood regeneration programme, works have been carried out at the junction of A5 Edgware Road and Geron Way to deliver improvements to the highway in the area.
The works included widening the junction and improving footways and street lighting to address safety concerns raised to us by residents. We also added a new pedestrian crossing at this junction to make it safer for people to cross this part of the road.
To minimise disruption from works in the area, these highways improvements have been planned so that they are almost complete by November, in time for when the main construction works on the new Waste Transfer Station begin. For more details on the new planned Waste Transfer Station visit the project page here.

Work schedule
Work commenced: Monday 19 May 2025
Contractors: FM Conway
Work Hours:
- Monday to Fridays between 8am to 6pm and 8am to 1pm on Saturdays.
- Occasionally we will need to undertake overnight works between 8pm and 5am. Residents will be notified in advance.
Geron Way junction works are near completion, and here’s what has taken place since July:
- The first phase of works included widening the junction and improving footways and street lighting.
- The second phase of works consisted of road resurfacing and replacing road markings on Edgware Road and Geron Way. These works were undertaken overnight during September 2025 and residents and businesses received send letters in advance.
- Humber Road (SC) bus stop has been relocated to approximately 150 metres south of the existing stop.
- New traffic signals at the junction have been installed.
- Drainage improvements and the resurfacing of the road.